House Raising Cost Calculator

Work out what it costs to lift a house, whether you are gaining legal head height underneath, escaping a flood level, or simply replacing failing stumps while the house is up.

m2

Ground floor footprint only, measured to the outside of the walls, including verandahs that will be lifted.

Masonry houses can be lifted but need extensive steel bracing, which is why the cost jumps.

Estimated house raising cost · NSW$63,750$93,700Indicative estimate only
What’s affecting your estimate
2.4m to 3m (legal head height)
How your estimate comparesTypical range
$48,600typical job$151,200

💡The house raiser is only one of the trades involved. Plumbing and drainage disconnection and reconnection, electrical disconnection and rewiring of the descent, and the stair build are all separate contracts, and together they commonly add $18,000 to $40,000 to the raiser's price.

💡You cannot live in the house while it is up on jacks. Budget six to twelve weeks of alternative accommodation from the day services are disconnected, which for a family in a capital city is typically $6,000 to $18,000 that never appears on any builder quote.

💰 Ways to save
  • Lift once and lift high enough. The marginal cost of going from a 1.8 metre lift to a legal 2.4 metre head height is modest because the jacking, cribbing and re-levelling labour is nearly identical, yet the value difference is enormous. Coming back in five years to lift the same house again costs almost the full amount a second time.
  • Do the restumping in the same operation as the raise, even if the existing stumps have a few years left in them. The house is already off its footings and fully cribbed, which is the expensive part of restumping. Replacing stumps separately later means paying $12,000 to $25,000 to recreate a condition you already had.
  • Get a full geotechnical report before you accept any quote. Reactive clay, fill or a high water table changes the footing design from simple pad footings to bored piers, and that can swing the substructure cost by $15,000 to $40,000. A $1,500 soil test upfront is the cheapest risk management available on this kind of project.
  • Consider leaving the underneath open initially and building in later as a staged approval. Enclosing and fitting out the ground level is where most of the money goes, and staging it lets you occupy the house sooner, spread the cost over two financial years, and avoid carrying construction finance on the whole project at once.

or from $376/week over 5 years , indicative finance

Run a renovation business? Put a calculator like this on your own website, branded as yours.See how →
How we estimate this

## What house raising costs in Australia in 2026

Pricing reviewed: June 2026.

Doing more than just house raising?

Build a combined estimate across every part of your project in one place.

Home Renovation Quote Builder

Pricing reviewed June 2026. Indicative Australian costs, not a quote.

Are you a renovation business?

Put this calculator on your own website, branded to you, visitors get an instant estimate, you get a qualified enquiry with their details.

See how it works →

Understanding house raising costs in Australia

What house raising costs in Australia in 2026

Raising a standard timber framed house of about 130 square metres to legal head height, with new steel posts on pad footings, generally costs between $60,000 and $95,000 in south east Queensland and northern New South Wales where the trade is most established. In Melbourne and Sydney the same job typically runs $75,000 to $120,000 because there are fewer specialist contractors and site access is usually tighter.

A simple lift and relevel of under a metre, essentially a restumping exercise with a modest height gain, is a much smaller project at $28,000 to $50,000. At the other end, lifting a large 200 square metre home over 3 metres to create a full storey underneath can reach $130,000 to $180,000 for the structural work alone, before any of the space beneath is enclosed.

The three phases of the project

Phase one is disconnection and preparation. Services are cut, the house is separated from its existing stumps or piers, and steel bearers are threaded underneath. This is where a masonry or brick veneer house becomes expensive, because the walls have no ability to span and must be needled and braced continuously.

Phase two is the lift itself. Hydraulic jacks raise the house in increments of a few hundred millimetres, with timber cribbing stacked under it at each stage. A straightforward lift takes one to three days of actual jacking, and it is genuinely less than 15 per cent of the total cost.

Phase three is the new substructure and reconnection. New footings are dug and poured, posts or piers are installed, the house is lowered onto them and packed level, and then the plumber, electrician and carpenter come back to reconnect services and build the new stair. This phase is where the bulk of the money and almost all of the time goes.

What the wall construction does to your price

Timber framed weatherboard and chamferboard houses are the ideal candidates. They are light, they flex without cracking, and the trade in Queensland has been lifting them for a century. These are the houses that sit at the bottom of the price range.

Brick veneer adds roughly 30 to 40 per cent. The frame lifts fine but the brick skin has to be supported independently or removed and relaid, and the articulation joints will crack regardless of how carefully it is done. Full masonry and double brick adds 70 to 100 per cent and requires a much more elaborate steel grid, and some raisers will decline the work outright.

Fibro clad houses raise easily because they are light, but pre 1990 sheeting is asbestos containing material. Sheets crack during a lift more often than not, and once you are into licensed removal you are frequently better off recladding the entire house while it is up, at $18,000 to $35,000.

Building in underneath

The reason most people raise a house is the space it creates. Simply pouring a slab and closing in the perimeter as a garage or storage shell costs roughly $35,000 to $55,000 for a typical footprint. Creating fully compliant habitable rooms with insulation, waterproofing, glazing, wet areas and finishes is a different order of project at $1,800 to $2,600 per square metre, so $150,000 to $250,000 for a 100 square metre ground level.

That fit out is a full development application in almost every council, and the requirements catch people out. You need 2.4 metres finished ceiling height in habitable rooms, which is why the lift itself needs to be around 3 metres once you account for slab thickness, floor build up and the existing bearer depth. Getting the lift height wrong by 200 millimetres can render the whole space unapprovable.

The costs that sit outside the raiser quote

Plumbing disconnection and reconnection with new vertical runs is $8,000 to $18,000. Electrical disconnection, a new descent to the switchboard and compliance certification is $6,000 to $14,000. A new external or internal stair to the raised entry level is $8,000 to $20,000 depending on materials and whether it is covered.

Then there is accommodation. Services are off for six to twelve weeks on a typical lift and restump, longer if you are building in underneath. Renting a comparable house in a capital city for that period is $6,000 to $18,000, and it is the single most commonly forgotten line item in the whole project.

Engineering and approvals add $6,000 to $15,000 for a straight lift and considerably more where new living space is involved. A structural engineer must design the new footings and the lifting methodology, and a certifier signs off the finished work.

Is it worth doing

In flood affected areas the answer is often driven by insurance rather than amenity. Lifting above the defined flood level can move a property from uninsurable or heavily loaded premiums into standard cover, and in some catchments government resilience programs have contributed toward the cost.

For everyone else the test is simple: compare the fully loaded cost of raising and building in underneath against the cost of a ground level extension or a second storey addition on the same block. Raising usually wins where the block is small, where setbacks prevent building outward, and where the existing house has good bones and character worth keeping. It rarely wins where the house itself is in poor condition, because you end up spending significant money to preserve something that needed replacing anyway.

Frequently asked questions

How much does it cost to raise a house in Australia?

A standard 130 square metre timber framed house lifted to legal head height with new steel posts costs $60,000 to $95,000 in south east Queensland and $75,000 to $120,000 in Sydney or Melbourne. A minor lift and relevel under one metre is $28,000 to $50,000, while a large home lifted over 3 metres can reach $130,000 to $180,000.

Can a brick house be raised?

Yes, but it costs substantially more. Brick veneer adds roughly 30 to 40 per cent because the brick skin needs independent support and will crack at articulation joints. Full double brick adds 70 to 100 per cent and requires an extensive steel needle beam grid, and some contractors decline masonry work entirely.

How long does house raising take?

The jacking itself takes one to three days. The full project from service disconnection to reconnection runs six to twelve weeks for a lift and restump, and four to nine months if you are building in habitable space underneath. You cannot occupy the house during the lift, so budget accommodation for the whole disconnected period.

How high do I need to lift to get a legal room underneath?

You need 2.4 metres of finished ceiling height in habitable rooms, which after a 100mm slab, floor coverings and the existing bearer and joist depth means lifting the house roughly 2.9 to 3.1 metres. Getting this wrong by 200 millimetres can make the entire ground level unapprovable, so have the engineer set the lift height from the finished floor level down.

Do I need council approval to raise a house?

Yes in every state. A straight lift and restump requires structural engineering and either a building approval or a development approval depending on the jurisdiction and whether the building height changes. Approvals and engineering typically cost $6,000 to $15,000 for a simple lift and $8,000 to $20,000 more where new living space is created.

What extra costs are not in the house raiser quote?

Plumbing reconnection at $8,000 to $18,000, electrical at $6,000 to $14,000, a new stair at $8,000 to $20,000, engineering and approvals at $6,000 to $15,000, and accommodation for six to twelve weeks at $6,000 to $18,000. Together these commonly add $35,000 to $80,000 on top of the raiser figure.